TASK 72-32-05-100-001 PTO Carrier Seal - Clean, Cleaning-001

DMC:V2500-A0-72-32-0504-00A-251A-C|Issue No:001.00|Issue Date:2013-11-01

Export Control

EAR Export Classification: Not subject to the EAR per 15 C.F.R. Chapter 1, Part 734.3(b)(3), except for the following Service Bulletins which are currently published as EAR Export Classification 9E991: SBE70-0992, SBE72-0483, SBE72-0580, SBE72-0588, SBE72-0640, SBE73-0209, SBE80-0024 and SBE80-0025.

Copyright

© IAE International Aero Engines AG (2001, 2014 - 2021) The information contained in this document is the property of © IAE International Aero Engines AG and may not be copied or used for any purpose other than that for which it is supplied without the express written authority of © IAE International Aero Engines AG. (This does not preclude use by engine and aircraft operators for normal instructional, maintenance or overhaul purposes.).

Applicability

All

Common Information

TASK 72-32-05-100-001 PTO Carrier Seal - Clean, Cleaning-001

Effectivity

FIG/ITEM

PART NO.

01-170

5A1328

01-170

5A0427

General

This TASK gives the procedure to clean the PTO carrier seal. For the other PTO drive shaft bearing and support parts, refer to TASK 72-32-05-100-000.

The practices and processes referred to in the procedure by the TASK numbers are in the SPM.

Fig/item numbers in parentheses in the procedure agree with those used in the IPC.

Reference

Refer to the SPM TASK 70-10-00-100-501 Cleaning - General Information.

Preliminary Requirements

Pre-Conditions

NONE

Support Equipment

NONE

Consumables, Materials and Expendables

NONE

Spares

NONE

Safety Requirements

NONE

Procedure

    1. SUBTASK 72-32-05-110-051 Remove the Soft Dirt and Dust

      1. Remove the soft dirt and dust. Refer to the SPM TASK 70-11-26-300-503

      2. Use a soft bristle brush or swab.

      1. Dry.

      2. Use clean dry air blast.

Requirements After Job Completion

Follow-On Conditions

NONE