TASK 72-41-00-200-013-B00 HPC Assembly - Do An Inspection After A HPC VSV Lever Fracture Failure, Inspection-002

DMC:V2500-A5-72-41-0000-02B-300A-B|Issue No:001.00|Issue Date:2013-11-01

Export Control

EAR Export Classification: Not subject to the EAR per 15 C.F.R. Chapter 1, Part 734.3(b)(3), except for the following Service Bulletins which are currently published as EAR Export Classification 9E991: SBE70-0992, SBE72-0483, SBE72-0580, SBE72-0588, SBE72-0640, SBE73-0209, SBE80-0024 and SBE80-0025.

Copyright

© IAE International Aero Engines AG (2001, 2014 - 2021) The information contained in this document is the property of © IAE International Aero Engines AG and may not be copied or used for any purpose other than that for which it is supplied without the express written authority of © IAE International Aero Engines AG. (This does not preclude use by engine and aircraft operators for normal instructional, maintenance or overhaul purposes.).

Applicability

V2500-A5

Common Information

TASK 72-41-00-200-013-B00 HPC Assembly - Do An Inspection After A HPC VSV Lever Fracture Failure, Inspection-002

General

This TASK gives the inspection procedure, during the disassembly of the HP compressor, following a HPC VSV Lever Fracture Failure.

All Fig/item numbers in the procedure agree with those used in the IPC. Only the primary Fig/item numbers are used. For the service bulletin alpha variants refer to the IPC.

For all parts identified in a different Chapter/Section/Subject, the applicable Chapter/Section/Subject comes before the Fig/item number.

References

Refer to the SPM for data on these items.

Definition of Damage, SPM TASK 70-02-02-350-501.

Record and Control of the Lives of Parts, SPM TASK 70-05-00-200-501.

Inspection of parts, SPM TASK 70-20-01-220-501.

Preliminary Requirements

Pre-Conditions

NONE

Support Equipment

NONE

Consumables, Materials and Expendables

NONE

Spares

NONE

Safety Requirements

NONE

Procedure

    1. SUBTASK 72-41-00-220-185 Examine the HPC VSV Lever Fracture Engines

    2. Refer to: Figure

      1. Where engines have sustained HPC VSV lever fractures, the HPC rotor blades must be rejected as follows:

        1. VIGV lever fracture.

        2. Replace all stage 3 blades HPC Rotor Blades (72-41-15, 01-200).

        1. Stage 3 lever fracture.

        2. Replace all stage 3 and 4 blades HPC Rotor Blades (72-41-15, 01-200 , HPC Rotor Blades01-500).

        1. Stage 4 lever fracture.

        2. Replace all stage 4 and 5 blades HPC Rotor Blades (72-41-15, 01-500 , HPC Rotor Blades01-800).

        1. Stage 5 lever fracture.

        2. Replace all stage 5 and 6 blades HPC Rotor Blades (72-41-15, 01-800 and HPC Rotor Blades72-41-15, 02-170, HPC Rotor Blades02-185, HPC Rotor Blades02-200, HPC Rotor Blades02-215, HPC Rotor Blades02-217).

  1. Figure: Examine the HPC Lever Fracture Engines

    Examine the HPC Lever Fracture Engines

Requirements After Job Completion

Follow-On Conditions

NONE